BHP Billiton Wharf Upgrade - PACE Marine Works

The wharf was the last stage of transportation infrastructure for the exportation of iron ore from Newman. Prior to its arrival at the wharf, the iron ore travels along the ‘PACE’ (Product and Capacity Expansion) project rail line from inland Western Australia.

The scope of the project included the construction of 375-metre long, piled iron ore berth, nine berthing dolphins, 108-metre approach jetty and 58 x 38-metre transfer platforms and associated conveyors.

Customer
BHP Billiton
Location
Port Headland, Western Australia
Start
September 2002
End
January 2004
Specialisation
Ports & marine

Despite initial difficulties, our team made modifications to their methodology and improved their productivity to deliver on time.